Update autodev state, architecture documentation, and glossary terms
Transitioned the autodev state to phase 21, reflecting the completion of Step 5 and the drafting of Step 6 epics. Revised the architecture documentation to clarify the roles of the Tile Manager and its components, ensuring accurate representation of the system's operational flow. Updated glossary entries for Flight State and Operator to incorporate recent changes and enhance clarity on component interactions and responsibilities.
This commit is contained in:
@@ -103,7 +103,7 @@ Coverage clears the 75% gate with margin under both the inclusive reading (PARTI
|
||||
These insights from Phase 2 augment the F1-F5 carried over from Phase 1; together they feed forward into Solution Analysis (Step 2) and Component Decomposition (Step 3):
|
||||
|
||||
1. **F6 — Two-tier execution profile is a first-class architectural concern.** The split between Tier-1 (workstation Docker) and Tier-2 (Jetson hardware) means several AC have validation locations that must appear in the deployment plan and in the CI matrix design. Add a "Tier-2 hardware-runner availability" entry to the project's risk register (Step 4).
|
||||
2. **F7 — `mock-suite-sat-service` is a real testing-time dependency that must be documented as a component boundary (not just a test fixture).** It encodes the publish-side of D-PROJ-2 and feeds into both NFT-SEC-01 and FT-P-17. Component decomposition (Step 3) should treat the Service-publish contract as an explicit C8/C10 cross-cutting boundary, not buried inside C8.
|
||||
2. **F7 — `mock-suite-sat-service` is an e2e-test fixture for the not-yet-shipped D-PROJ-2 POST contract.** It is **not a first-class component** (ADR-007 reversed 2026-05-09); the architectural counterparty for both download and upload is the real `satellite-provider`. The contract sketch is the source of truth and lives in `_docs/_process_leftovers/2026-05-09_satellite-provider-design-tasks.md`; the fixture mirrors it for NFT-SEC-01 / FT-P-17 / IT runs and is retired when the real endpoint ships. Component decomposition (Step 3) treats the Service-publish contract as a C11 `TileUploader` ↔ `satellite-provider` boundary (not buried inside C8).
|
||||
3. **F8 — VioStrategy parameterization in CI requires both a production binary AND a research binary.** D-C1-1-SUB-A locked the BUILD_VINS_MONO=ON/OFF split; the test plan must produce both binaries on every PR for the comparative-study report (IT-12 in `solution.md`). Add to deployment plan (Step 2) and to epic/work-item planning (Step 6).
|
||||
4. **F9 — D-PROJ-3 (fixture acquisition) is now a named deliverable** with a clear gate: must resolve before greenfield Step 5 re-runs the full test-spec with architecture context. Promote to risk register and to the architecture's open-items list.
|
||||
5. **F10 — Defense-in-depth security layer (NFT-SEC-05 DNS blackholing, OPENCV ASan build, SBOM signing-passkey verification)** implies CI/build infrastructure features (multi-stage build for ASan instrumentation, SBOM generator, lockfile linter). Add to deployment plan (Step 2).
|
||||
|
||||