Date: 2026-05-03 Total Tasks: 14 Total Complexity Points: 60 Lessons applied: No _docs/LESSONS.md file exists; no prior estimation or dependency lessons were available.

Task Name Complexity Dependencies Epic
AZ-219 initial_structure 5 None AZ-206
AZ-220 shared_runtime_contracts 3 AZ-219 AZ-206
AZ-221 shared_geometry_time_sync 3 AZ-219, AZ-220 AZ-207
AZ-222 runtime_config_errors_telemetry 3 AZ-219, AZ-220 AZ-208
AZ-223 camera_ingest_calibration 5 AZ-220, AZ-221, AZ-222 AZ-209
AZ-224 mavlink_gcs_gateway 3 AZ-220, AZ-222 AZ-210
AZ-225 tile_manager_cache_manifest 5 AZ-220, AZ-221, AZ-222 AZ-211
AZ-226 generated_tile_orthorectification 5 AZ-223, AZ-225 AZ-211
AZ-227 fdr_event_recorder 5 AZ-220, AZ-222 AZ-212
AZ-228 basalt_vio_adapter 5 AZ-221, AZ-222, AZ-223, AZ-224 AZ-213
AZ-229 satellite_service_sync 3 AZ-222, AZ-225, AZ-226 AZ-214
AZ-230 satellite_service_vpr_retrieval 5 AZ-223, AZ-225, AZ-229 AZ-214
AZ-231 anchor_verification_matching 5 AZ-223, AZ-225, AZ-230 AZ-215
AZ-232 safety_anchor_state_machine 5 AZ-223, AZ-224, AZ-227, AZ-228, AZ-231 AZ-216

Verification Notes

  • No task exceeds 5 complexity points.
  • E2E/blackbox test work remains outside this product implementation task set and is deferred to the greenfield Decompose Tests phase.
  • The graph is acyclic: foundations precede adapters/stores, then VIO/retrieval/matching, then safety wrapper orchestration.