[AZ-491] [AZ-492] [AZ-493] [AZ-494] [AZ-495] [AZ-496] Cycle 3 Step 17: retrospective + close cycle
Cycle-3 retrospective:
- 6 tasks (AZ-491..AZ-496), 5 batches, 18 SP delivered.
- 100% code review pass rate (5/5 PASS_WITH_WARNINGS, 0 FAIL).
- 0 Critical/High/Medium review findings; 7 distinct Low.
- Security audit PASS_WITH_WARNINGS: 0 new Medium, 3 Low (all
test-only or operator-CLI), 2 Informational, 1 False Positive.
- Net Architecture delta: **-3** (F-AUTH-2 + D1 + D3 RESOLVED;
only new findings are Low test-side surfaces). First
net-negative cycle on record.
- 5 of 6 tasks completed first attempt (no post-review fix
commits). Cycle-2's 2 prior-retro actions all translated to
closed work (AZ-491 from Action 1, AZ-492 from Action 2,
AZ-493 from Action 3).
Top 3 cycle-4 improvement actions surfaced:
1. Execute the perf harness to capture PT-07/PT-08 baseline.
2. Bump TestSupport JWT pins 7.0.3 → 7.1.2+ (D4 NU1902 cleanup).
3. Add `workspace:` tag to cross-repo ACs in task-spec writing
and render them separately in the traceability matrix.
3 new ring-buffer lessons appended to _docs/LESSONS.md:
- [process] Option-B forcing functions for cross-team blockers.
- [process] ACs prescribing a measurement should also prescribe
the collection path.
- [process] Cross-repo-write ACs need workspace tags.
Structural snapshot at structure_2026-05-12_cycle3.md records the
new SatelliteProvider.TestSupport project (+2 ProjectReference edges
into it; no production-layer dependents) and the AZ-496 package
bumps (8.0.21 → 8.0.25).
Cycle 3 COMPLETE. State advanced to Step 9 (New Task) for cycle 4
per existing-code flow Re-Entry After Completion.
Co-authored-by: Cursor <cursoragent@cursor.com>
This commit is contained in:
@@ -37,6 +37,12 @@ If the enum's wire string happens to match a member name case-insensitively (e.g
|
||||
|
||||
## Ring buffer (last 15 entries — newest at top)
|
||||
|
||||
- [2026-05-12] [process] For cross-team blockers (admin team must supply config values, etc.), prefer an Option-B forcing function (ship the validation/scaffolding with prod-empty config that fails-fast at deploy) over deferring the entire task — the fail-fast contract makes the cross-team conversation impossible to skip and ships the in-workspace work in the current cycle (cycle 3: AZ-494 shipped iss/aud validation with empty prod appsettings so deploy must supply real values).
|
||||
Source: _docs/06_metrics/retro_2026-05-12_cycle3.md
|
||||
- [2026-05-12] [process] ACs that prescribe a specific measurement or sentinel mechanism (e.g. "per-item latency < 50ms", "guard fires when DB name contains _test") should also prescribe — or explicitly defer — the path for collecting / enforcing it, or implementations will substitute proxies / equivalents that look like spec drift in review (cycle 3: AZ-492 PT-08 per-item gate cost became a derived proxy; AZ-493 DB-name guard became Host-allowlist).
|
||||
Source: _docs/06_metrics/retro_2026-05-12_cycle3.md
|
||||
- [2026-05-12] [process] ACs that require cross-repo writes should be tagged with the target workspace and rendered separately in the traceability matrix — mixing them with in-workspace ACs makes "correctly deferred" indistinguishable from "incomplete work" (cycle 3: AZ-494 AC-7 deferred for the suite-repo write; matrix renders as `◐ deferred` which is ambiguous).
|
||||
Source: _docs/06_metrics/retro_2026-05-12_cycle3.md
|
||||
- [2026-05-11] [testing] Test helpers shared across unit + integration projects must live in one consolidated location — duplicate near-identical copies will diverge and require parallel fixes (cycle 2: `JwtTokenFactory.cs` and `JwtTestHelpers.cs` had the same `Expires < NotBefore` bug fixed in separate commits).
|
||||
Source: _docs/06_metrics/retro_2026-05-11_cycle2.md
|
||||
- [2026-05-11] [process] Deferred-status NFR entries are allowed at most ONCE per NFR — if a Deferred NFR has not landed by the end of the cycle that follows the one in which it was deferred, the harness work must be promoted to a real PBI before any new NFR is accepted as Deferred (cycle 2 inherited cycle 1's PT-07 + added PT-08 + JWT-attach script-rot).
|
||||
|
||||