Implementation Completeness — Cycle 15

Date: 2026-06-26 Cycle: 15 Tasks: AZ-1132

Per-Task Classification

Task Classification Evidence
AZ-1132 PASS csproj pins 12.1.1; docs + security artifacts updated; validator unit tests green

System Pipeline Audit

No new pipelines introduced. Dependency-only change — N/A.

Gate Verdict

PASS — proceed to Step 11 (Run Tests).