Oleksandr Bezdieniezhnykh 6b373082c8 [AZ-315] Sync architecture docs after coupling refactor
Phase C of architecture coupling refactor (epic AZ-309). Closes the
last baseline finding (F5 — DataAccess incorrectly documented as
importing Common) and synchronizes the rest of _docs/02_document/
with the post-split project layout from AZ-312/313/314:

- module-layout.md: per-component sections for the three new csprojs
  with explicit ProjectReferences and the no-cross-sibling-reference
  invariant the split enforces.
- architecture.md: components and internal-communication tables
  updated to show calls flow through Common interfaces.
- architecture_compliance_baseline.md: F1..F5 marked Resolved with
  task IDs and commit refs; baseline summary now 0 findings.
- diagrams/components.md, components/03_tile_downloader/description.md,
  modules/{common_interfaces,services_tile_service,
  services_google_maps_downloader,tests_unit}.md updated for the
  split, RateLimitException relocation, and new ITileService methods.

Documentation-only batch — no code, no tests, no build changes.
Epic AZ-309 complete (6 tasks across 3 batches).

Co-authored-by: Cursor <cursoragent@cursor.com>
2026-05-10 07:25:21 +03:00

2.0 KiB

Task Dependencies

Dependency Graph

Step 6 — Implement Tests (AZ-285..AZ-290)

Task Depends On Points Status
AZ-285 Test Infrastructure 3 Done
AZ-286 TileService Tests AZ-285 3 Done
AZ-287 RegionService Tests AZ-285 3 Done
AZ-288 RouteService Tests AZ-285 3 Done
AZ-289 Integration Route Maps AZ-285 2 Done
AZ-290 Non-Functional Tests AZ-285 3 Done

Step 8 — Refactor 02-coupling-refactoring (AZ-309 epic)

Task Depends On Points Status
AZ-310 ServeTile via ITileService 3 Done (In Testing)
AZ-311 GetTileByLatLon via ITileService AZ-310 2 Done (In Testing)
AZ-312 Split Services into 3 csprojs AZ-311 5 Done (In Testing)
AZ-313 Update consumers (Api/Tests) AZ-312 3 Done (In Testing)
AZ-314 DI registration split AZ-313 2 Done (In Testing)
AZ-315 Documentation sync AZ-314 2 In Progress

Execution Order

Step 6

  1. AZ-285 (test infrastructure — all others depend on this)
  2. AZ-286, AZ-287, AZ-288 (unit tests — can run in parallel)
  3. AZ-289 (integration tests — depends on infra only)
  4. AZ-290 (non-functional tests — depends on infra only)

Step 8 (refactor)

  1. AZ-310 → AZ-311 (Phase A: route tile endpoints through ITileService)
  2. AZ-312 → AZ-313 → AZ-314 (Phase B: physical split + consumer + DI rewire)
  3. AZ-315 (Phase C: docs sync, must be last)

Total Effort

Step 6: 6 tasks, 17 story points Step 8 (refactor): 6 tasks, 17 story points

Coverage Verification

Test Spec Category Covered By
blackbox-tests.md (BT-01..BT-12, BT-N01..BT-N05) AZ-286, AZ-287, AZ-288, AZ-289
performance-tests.md (PT-01..PT-06) AZ-290
resilience-tests.md (RS-01..RS-06) AZ-290
security-tests.md (SEC-01..SEC-04) AZ-290
resource-limit-tests.md (RL-01..RL-04) AZ-290
traceability-matrix.md (100% AC coverage) All tasks combined