Files
gps-denied-desktop/_docs/00_templates/quality_gates.md
T
Oleksandr Bezdieniezhnykh fd75243a84 more detailed SDLC plan
2025-12-10 19:05:17 +02:00

3.4 KiB

Quality Gates

Quality gates are checkpoints that must pass before proceeding to the next phase.


Kickstart Tutorial Quality Gates

Gate 1: Research Complete (after 1.40)

Before proceeding to Planning phase:

  • Problem description is clear and complete
  • Acceptance criteria are measurable and testable
  • Restrictions are documented
  • Security requirements defined
  • Solution draft reviewed and finalized
  • Tech stack evaluated and selected

Gate 2: Planning Complete (after 2.40)

Before proceeding to Implementation phase:

  • All components defined with clear boundaries
  • Data model designed and reviewed
  • API contracts defined
  • Test specifications created
  • Jira epics/tasks created
  • Effort estimated
  • Risks identified and mitigated

Gate 3: Implementation Complete (after 3.40)

Before merging to main:

  • All components implemented
  • Code coverage >= 75%
  • All tests pass (unit, integration)
  • Code review approved
  • Security scan passed
  • CI/CD pipeline green
  • Deployment tested on staging
  • Documentation complete

Iterative Tutorial Quality Gates

Gate 1: Spec Ready (after step 20)

Before creating Jira task:

  • Building block clearly defines problem/goal
  • Feature spec has measurable acceptance criteria
  • Dependencies identified
  • Complexity estimated

Gate 2: Implementation Ready (after step 50)

Before starting development:

  • Plan reviewed and approved
  • Test strategy defined
  • Dependencies available or mocked

Gate 3: Merge Ready (after step 70)

Before creating PR:

  • All acceptance criteria met
  • Tests pass locally
  • Definition of Done checklist completed
  • No unresolved TODOs in code

Refactoring Tutorial Quality Gates

Gate 1: Safety Net Ready (after 4.50)

Before starting refactoring:

  • Baseline metrics captured
  • Current behavior documented
  • Integration tests pass (>= 75% coverage)
  • Feature parity checklist created

Gate 2: Refactoring Safe (after each 4.70 cycle)

After each refactoring step:

  • All existing tests still pass
  • No functionality lost (feature parity check)
  • Performance not degraded (compare to baseline)

Gate 3: Refactoring Complete (after 4.95)

Before declaring refactoring done:

  • All tests pass
  • Performance improved or maintained
  • Security review passed
  • Technical debt reduced
  • Documentation updated

Automated Gate Checks

CI Pipeline Gates

gates:
  build:
    - compilation_success: true
  
  quality:
    - lint_errors: 0
    - code_coverage: ">= 75%"
    - code_smells: "< 10 new"
  
  security:
    - critical_vulnerabilities: 0
    - high_vulnerabilities: 0
  
  tests:
    - unit_tests_pass: true
    - integration_tests_pass: true

Manual Gate Checks

Some gates require human verification:

  • Architecture review
  • Security review
  • UX review (for UI changes)
  • Stakeholder sign-off

Gate Failure Handling

When a gate fails:

  1. Stop - Do not proceed to next phase
  2. Identify - Determine which checks failed
  3. Fix - Address the failures
  4. Re-verify - Run gate checks again
  5. Document - If exception needed, get approval and document reason

Exception Process

If a gate must be bypassed:

  1. Document the reason
  2. Get tech lead approval
  3. Create follow-up task to address
  4. Set deadline for resolution