Refactor documentation to replace the Validation Harness with a separate E2E Test Suite, updating references throughout various documents. Adjust the autodev state to reflect the transition from the Decompose phase to the Implement phase, and revise the architecture documentation to clarify system boundaries and component relationships. Enhance risk mitigation documentation to specify affected components and update the component overview diagram accordingly.

This commit is contained in:
Oleksandr Bezdieniezhnykh
2026-05-03 11:50:39 +03:00
parent 5bf2dbd85f
commit dd9afe2797
31 changed files with 1479 additions and 396 deletions
+29
View File
@@ -0,0 +1,29 @@
# Dependencies Table
**Date**: 2026-05-03
**Total Tasks**: 14
**Total Complexity Points**: 60
**Lessons applied**: No `_docs/LESSONS.md` file exists; no prior estimation or dependency lessons were available.
| Task | Name | Complexity | Dependencies | Epic |
|------|------|------------|--------------|------|
| AZ-219 | initial_structure | 5 | None | AZ-206 |
| AZ-220 | shared_runtime_contracts | 3 | AZ-219 | AZ-206 |
| AZ-221 | shared_geometry_time_sync | 3 | AZ-219, AZ-220 | AZ-207 |
| AZ-222 | runtime_config_errors_telemetry | 3 | AZ-219, AZ-220 | AZ-208 |
| AZ-223 | camera_ingest_calibration | 5 | AZ-220, AZ-221, AZ-222 | AZ-209 |
| AZ-224 | mavlink_gcs_gateway | 3 | AZ-220, AZ-222 | AZ-210 |
| AZ-225 | tile_manager_cache_manifest | 5 | AZ-220, AZ-221, AZ-222 | AZ-211 |
| AZ-226 | generated_tile_orthorectification | 5 | AZ-223, AZ-225 | AZ-211 |
| AZ-227 | fdr_event_recorder | 5 | AZ-220, AZ-222 | AZ-212 |
| AZ-228 | basalt_vio_adapter | 5 | AZ-221, AZ-222, AZ-223, AZ-224 | AZ-213 |
| AZ-229 | satellite_service_sync | 3 | AZ-222, AZ-225, AZ-226 | AZ-214 |
| AZ-230 | satellite_service_vpr_retrieval | 5 | AZ-223, AZ-225, AZ-229 | AZ-214 |
| AZ-231 | anchor_verification_matching | 5 | AZ-223, AZ-225, AZ-230 | AZ-215 |
| AZ-232 | safety_anchor_state_machine | 5 | AZ-223, AZ-224, AZ-227, AZ-228, AZ-231 | AZ-216 |
## Verification Notes
- No task exceeds 5 complexity points.
- E2E/blackbox test work remains outside this product implementation task set and is deferred to the greenfield Decompose Tests phase.
- The graph is acyclic: foundations precede adapters/stores, then VIO/retrieval/matching, then safety wrapper orchestration.