# Traceability Matrix
|
|
|
|
This matrix is the canonical view of test coverage for the planning context. It traces every numbered AC and every restriction to the test scenario IDs that exercise it.
|
|
|
|
**Coverage discipline**: an AC counts as **Covered** when at least one test scenario has a quantifiable pass/fail criterion that exercises it. **PARTIAL** rows are exercised but with reduced confidence — the row's "Mitigation" column points to the action item (Plan-phase decision or D-PROJ gate) that, when resolved, lifts the row to Covered. **NOT COVERED** rows are deliberately deferred (out-of-scope for data acquisition per Phase 1 gate, or covered at a later workflow stage); each has a stated mitigation.
|
|
|
|
## Acceptance Criteria Coverage
|
|
|
|
| AC ID | Acceptance Criterion (one-line) | Test IDs | Coverage |
|
|
|-------|---------------------|----------|----------|
|
|
| AC-1.1 | Frame-center GPS within 50 m for ≥80% of normal-flight photos | FT-P-01 | Covered |
|
|
| AC-1.2 | Frame-center GPS within 20 m for ≥50% of normal-flight photos | FT-P-01 | Covered |
|
|
| AC-1.3 | Cumulative drift between satellite-anchored fixes <100 m visual / <50 m IMU-fused | FT-P-02 | Covered |
|
|
| AC-1.4 | Estimate reports 95% covariance + source label | FT-P-03 | Covered |
|
|
| AC-2.1a | Frame-to-frame registration ≥95% on normal segments | FT-P-04 | Covered |
|
|
| AC-2.1b | Satellite-anchor registration meets AC-1.1/1.2/2.2/8.2/8.6 | FT-P-05, FT-P-19 | Covered |
|
|
| AC-2.2 | MRE <1 px frame-to-frame, <2.5 px cross-domain | FT-P-05, FT-P-06 | Covered |
|
|
| AC-3.1 | Tolerate up to 350 m outliers, tilt ±20° | FT-N-01 | Covered |
|
|
| AC-3.2 | Tolerate sharp turns; recovery via satellite re-loc | FT-P-07, FT-N-02 | Covered |
|
|
| AC-3.3 | Handle ≥3 disconnected segments via satellite re-loc | FT-P-08 | Covered |
|
|
| AC-3.4 | On ≥3 frames + ≥2 s outage, request operator re-loc; FC dead-reckons | FT-N-03 | Covered |
|
|
| AC-3.5 | Visual blackout + spoofed GPS failsafe | FT-N-04 | Covered |
|
|
| AC-4.1 | E2E latency <400 ms p95 | NFT-PERF-01 (Tier-2), NFT-RES-05 (bootstrap precondition) | Covered |
|
|
| AC-4.2 | Memory <8 GB on Jetson | NFT-LIM-01 (Tier-2) | Covered |
|
|
| AC-4.3 | FC output contract: GPS_INPUT (AP) + MSP2_SENSOR_GPS (iNav) with honest covariance | FT-P-03, FT-P-09-AP, FT-P-09-iNav | Covered |
|
|
| AC-4.4 | Estimates streamed frame-by-frame | NFT-PERF-02 | Covered |
|
|
| AC-4.5 (revised) | Internal smoothing improves past-keyframe estimates (NOT FC retroactive correction per Mode B Fact #107) | FT-P-10 | Covered |
|
|
| AC-5.1 | Init from FC EKF's last valid GPS + IMU-extrapolated | FT-P-11 | Covered |
|
|
| AC-5.2 | On >3 s without estimate, FC IMU-only fallback; SUT logs | NFT-RES-01 | Covered |
|
|
| AC-5.3 | On reboot, re-init from FC IMU-extrapolated pose | NFT-RES-02 | Covered |
|
|
| AC-6.1 | GCS stream at 1-2 Hz | FT-P-12 | Covered |
|
|
| AC-6.2 | GCS may send commands via standard MAVLink | FT-P-13 | Covered |
|
|
| AC-6.3 | WGS84 output | FT-P-14 | Covered |
|
|
| AC-7.1 | AI-camera object localization, level-flight accuracy | — | NOT COVERED — out of scope for current data acquisition (no AI-camera fixture; AC-7.x scoped to a different sensor). Mitigation: defer to a follow-up cycle with AI-camera fixture; flag in `_docs/_process_leftovers/` as `2026-05-09_ai-camera-fixture-deferred.md` |
|
|
| AC-7.2 | AI-camera object coordinates from gimbal/zoom/altitude | — | NOT COVERED — same as AC-7.1 |
|
|
| AC-8.1 | Imagery via Suite Sat Service offline cache, ≥0.5 m/px | FT-P-15, FT-P-16, NFT-SEC-02 | Covered |
|
|
| AC-8.2 | Tile freshness <6 mo (active-conflict) / <12 mo (rear) | FT-N-05 | Covered |
|
|
| AC-8.3 | Imagery pre-loaded onto companion before flight | FT-P-15, FT-P-16 | Covered |
|
|
| AC-8.4 | Mid-flight tile generation with quality metadata | FT-P-17 | Covered |
|
|
| AC-8.5 | No raw nav/AI-cam frame retention except thumbnail log | FT-P-18 | Covered |
|
|
| AC-8.6 | Satellite relocalization scale-ratio + scene-change | FT-P-19 (scale FULL; scene-change PARTIAL) | PARTIAL — scene-change subset reduced confidence (only 2/60 stills have paired sat refs; no labeled change-pair dataset). Independent of the AC-NEW-4 / AC-NEW-7 multi-flight gap (those rows were resolved by AC-text relaxation 2026-05-09; AC-8.6 scene-change still requires a labeled change-pair dataset that synthetic perturbations cannot substitute for). Mitigation: deferred to a follow-up cycle when labeled change-pair data becomes available; surfaced in the Step 4 risk register |
|
|
| AC-NEW-1 | Cold-start TTFF <30 s p95 | NFT-PERF-03 (Tier-2), NFT-RES-05 (bootstrap precondition) | Covered |
|
|
| AC-NEW-2 | Spoofing-promotion latency <3 s p95 | NFT-PERF-04 | Covered |
|
|
| AC-NEW-3 | FDR ≤64 GB / flight, no silent drops | NFT-LIM-02 | Covered |
|
|
| AC-NEW-4 | False-position safety: P(>500 m)<0.1%, P(>1 km)<0.01% | NFT-RES-03 | Covered — AC text relaxed 2026-05-09 to Monte-Carlo-over-current-data with stated 95% CI (Plan Phase 2a.0 outcome). Multi-flight statistical headroom is residual risk in the Step 4 risk register; D-PROJ-3 reopens validation when additional multi-flight data becomes available |
|
|
| AC-NEW-5 | Operating envelope -20 °C to +50 °C, 25 W TDP, 8 h, no throttle | NFT-LIM-04 (workstation baseline only) | PARTIAL — workstation thermal-day baseline only. Mitigation: chamber-attached Jetson runner + DO-160G shaker rig — out of scope for data-acquisition per Phase 1 gate; tracked as a release-tag-blocking gate |
|
|
| AC-NEW-6 | System rejects/downgrades stale tiles | FT-N-05, FT-N-06 | Covered |
|
|
| AC-NEW-7 | Cache poisoning: P(misalign>30 m)<1%, P(>100 m)<0.1% | NFT-SEC-01 | Covered (onboard-side) — AC text relaxed 2026-05-09 to Monte-Carlo-over-current-data with stated 95% CI for the onboard contribution. Cross-suite voting-layer contract verification (D-PROJ-2) is a parent-suite design task tracked outside this Plan cycle; multi-flight statistical headroom remains residual risk (D-PROJ-3) |
|
|
| AC-NEW-8 | Visual blackout + spoof degraded-mode escalation | FT-N-04, NFT-RES-04 | Covered |
|
|
|
|
## Restrictions Coverage
|
|
|
|
| Restriction ID | Restriction (one-line) | Test IDs | Coverage |
|
|
|---------------|-------------|----------|----------|
|
|
| RESTRICT-UAV-1 | Fixed-wing UAV, nav-camera fixed downward | FT-N-01 (tilt envelope) | Covered (envelope assertion) |
|
|
| RESTRICT-UAV-2 | Mission profile: 8 h flights, 60 km/h, ≤400 km² area | NFT-LIM-01, NFT-LIM-02 (8 h replay) | Covered |
|
|
| RESTRICT-UAV-3 | Sharp turns may share <5% overlap | FT-P-07, FT-N-02 | Covered |
|
|
| RESTRICT-UAV-4 | No raw-photo storage; tile cache + FDR only | FT-P-18, NFT-LIM-03 | Covered |
|
|
| RESTRICT-CAM-1 | Nav camera ADTi 20MP 20L V1 nadir-fixed | FT-N-01 (tilt envelope), test fixture validation | Covered |
|
|
| RESTRICT-CAM-2 | AI camera: gimbal+zoom only; level-flight scope | — | NOT COVERED — paired with AC-7.x deferral |
|
|
| RESTRICT-SAT-1 | Onboard cache offline-only; no in-flight Service calls | FT-P-16, NFT-SEC-02, NFT-SEC-05 | Covered |
|
|
| RESTRICT-SAT-2 | Cache budget 10 GB across operational area | NFT-LIM-03 | Covered |
|
|
| RESTRICT-SAT-3 | Tile freshness per AC-8.2 / AC-NEW-6 | FT-N-05, FT-N-06 | Covered |
|
|
| RESTRICT-SAT-4 | No Sentinel-2 / sub-0.5 m/px imagery | FT-P-15 (resolution floor) | Covered |
|
|
| RESTRICT-HW-1 | Jetson Orin Nano Super, 8 GB shared LPDDR5, 25 W | NFT-LIM-01, NFT-LIM-04, NFT-LIM-05 | Covered |
|
|
| RESTRICT-HW-2 | Cooling 25 W continuous, 8 h, upper temp envelope | NFT-LIM-04, deferred chamber test | PARTIAL — chamber portion deferred; same as AC-NEW-5 |
|
|
| RESTRICT-FC-1 | ArduPilot Plane + iNav supported; PX4 out of scope | FT-P-09-AP, FT-P-09-iNav, parameterized matrix | Covered |
|
|
| RESTRICT-FC-2 | iNav has no inbound MAVLink ext-positioning; MSP2 only | FT-P-09-iNav | Covered |
|
|
| RESTRICT-FC-3 | Output contract: WGS84 GPS via per-FC interface | FT-P-09-AP, FT-P-09-iNav, FT-P-14 | Covered |
|
|
| RESTRICT-COMM-1 | MAVLink for GCS link (QGroundControl) | FT-P-12, FT-P-13 | Covered |
|
|
| RESTRICT-COMM-2 | iNav has no MAVLink signing; accepted residual risk | NFT-SEC-03 (asymmetry note) | Covered (documented asymmetry) |
|
|
| RESTRICT-FAIL-1 | >3 s no estimate → FC IMU-only fallback | NFT-RES-01 | Covered |
|
|
| RESTRICT-FAIL-2 | False-position safety budget (AC-NEW-4) | NFT-RES-03 | Covered (via AC-NEW-4 relaxation 2026-05-09); multi-flight statistical headroom is residual risk in Step 4 |
|
|
| RESTRICT-FAIL-3 | Cold-start TTFF (AC-NEW-1), spoofing-promotion (AC-NEW-2) | NFT-PERF-03, NFT-PERF-04 | Covered |
|
|
|
|
## Coverage Summary
|
|
|
|
> Revised 2026-05-09 (Plan Phase 2a.0 outcomes): three rows moved PARTIAL → Covered (AC-NEW-4, AC-NEW-7, RESTRICT-FAIL-2) following AC-text relaxation per Q3=B. Restriction row count corrected from 19 to 20 (pre-existing arithmetic error).
|
|
>
|
|
> Revised 2026-05-19 (Greenfield Step 12 cycle-update — autodev): NFT-RES-05 appended to `resilience-tests.md` capturing the composition-root bootstrap contract introduced by AZ-591 / AZ-618 / AZ-687 (replay-mode minimal config, `AirborneBootstrapError` operator-error contract, Tier-2 `replay.compose_root.ready` + `replay.input.frame_emitted` log-boundary gate). NFT-RES-05 is added to AC-NEW-1 and AC-4.1 as bootstrap-precondition coverage; no coverage counts move because the scenario is supplementary, not promoting any PARTIAL row.
|
|
|
|
| Category | Total Items | Covered | PARTIAL | Not Covered | Coverage % (Covered + PARTIAL counted half) |
|
|
|----------|-----------|---------|---------|-------------|--------------------------------------------|
|
|
| Acceptance Criteria | 39 | 35 | 2 | 2 | 92.3% |
|
|
| Restrictions | 20 | 18 | 1 | 1 | 92.5% |
|
|
| **Total** | **59** | **53** | **3** | **3** | **92.4%** |
|
|
|
|
Coverage clears the 75% gate with margin under both the inclusive reading (PARTIAL = covered) and the strict reading (PARTIAL not counted) — strict coverage is **(53 / 59) = 89.8%**. The remaining PARTIAL / Not Covered items are: AC-8.6 scene-change subset (needs labeled change-pair dataset, deferred), AC-NEW-5 hot-soak chamber (physical hardware, deferred), AC-7.1 / AC-7.2 (no AI-camera fixture, deferred), RESTRICT-CAM-2 (paired with AC-7.x), RESTRICT-HW-2 chamber portion (paired with AC-NEW-5).
|
|
|
|
## Uncovered Items Analysis
|
|
|
|
> Revised 2026-05-09 (Plan Phase 2a.0): AC-NEW-4 and AC-NEW-7 rows removed from this section after AC-text relaxation (Q3=B) flipped them to Covered with residual risk tracked in the Step 4 risk register.
|
|
|
|
| Item | Reason Not Covered | Risk | Mitigation |
|
|
|------|-------------------|------|-----------|
|
|
| AC-7.1 | No AI-camera fixture in `input_data/`; AC scoped to a different sensor than the nav camera; level-flight assumption + bank/pitch <5° is independent of the nav-cam pipeline | Object-localization accuracy untested; AI consumers may receive wrong coordinates if not flight-tested | Deferred to a follow-up Plan cycle scoped to AI-camera integration; recorded in `_docs/_process_leftovers/2026-05-09_ai-camera-fixture-deferred.md` (will be created in Phase 3 if confirmed). |
|
|
| AC-7.2 | Same as AC-7.1 | Same | Same |
|
|
| AC-8.6 (scene-change subset) | Only 2/60 stills paired with `_gmaps.png`; no labeled change-pair dataset bundled in `input_data/`. Independent of the AC-NEW-4 / AC-NEW-7 multi-flight gap (those were resolved by AC-text relaxation; AC-8.6 still needs labeled change-pair data) | Stale-tile match in active-conflict sectors may yield false `satellite_anchored`; AC-NEW-6 partially compensates but scene-change recall is unmeasured | Deferred to a follow-up cycle when labeled change-pair data becomes available (Maxar Open Data Ukraine + AerialVL change-pair subset). Scale-ratio half of AC-8.6 IS covered. |
|
|
| AC-NEW-5 | Workstation thermal-day baseline only. AC-NEW-5 hot-soak (25 W @ +50 °C, 8 h, no throttle) requires a thermal chamber — physical hardware, not data | Without chamber test, AC-4.1 latency budget at +50 °C is not validated; D-CROSS-LATENCY-1 hybrid auto-degrade unproven under real thermal stress | Chamber-attached Jetson runner gated as release-tag-blocker. NOT counted as data-acquisition deferral; counted as physical hardware deferral. |
|
|
| RESTRICT-CAM-2 | Paired with AC-7.x — no AI-camera fixture | Same as AC-7.x | Same as AC-7.x |
|
|
| RESTRICT-HW-2 (chamber portion) | Paired with AC-NEW-5 — physical chamber required | Same as AC-NEW-5 | Same as AC-NEW-5 |
|
|
|
|
## New findings forwarded into Plan (Steps 2 + 3 inputs)
|
|
|
|
These insights from Phase 2 augment the F1-F5 carried over from Phase 1; together they feed forward into Solution Analysis (Step 2) and Component Decomposition (Step 3):
|
|
|
|
1. **F6 — Two-tier execution profile is a first-class architectural concern.** The split between Tier-1 (workstation Docker) and Tier-2 (Jetson hardware) means several AC have validation locations that must appear in the deployment plan and in the CI matrix design. Add a "Tier-2 hardware-runner availability" entry to the project's risk register (Step 4).
|
|
2. **F7 — `mock-suite-sat-service` is an e2e-test fixture for the not-yet-shipped D-PROJ-2 POST contract.** It is **not a first-class component** (ADR-007 reversed 2026-05-09); the architectural counterparty for both download and upload is the real `satellite-provider`. The contract sketch is the source of truth and lives in `_docs/_process_leftovers/2026-05-09_satellite-provider-design-tasks.md`; the fixture mirrors it for NFT-SEC-01 / FT-P-17 / IT runs and is retired when the real endpoint ships. Component decomposition (Step 3) treats the Service-publish contract as a C11 `TileUploader` ↔ `satellite-provider` boundary (not buried inside C8).
|
|
3. **F8 — VioStrategy parameterization in CI requires both a production binary AND a research binary.** D-C1-1-SUB-A locked the BUILD_VINS_MONO=ON/OFF split; the test plan must produce both binaries on every PR for the comparative-study report (IT-12 in `solution.md`). Add to deployment plan (Step 2) and to epic/work-item planning (Step 6).
|
|
4. **F9 — D-PROJ-3 (fixture acquisition) is now a named deliverable** with a clear gate: must resolve before greenfield Step 5 re-runs the full test-spec with architecture context. Promote to risk register and to the architecture's open-items list.
|
|
5. **F10 — Defense-in-depth security layer (NFT-SEC-05 DNS blackholing, OPENCV ASan build, SBOM signing-passkey verification)** implies CI/build infrastructure features (multi-stage build for ASan instrumentation, SBOM generator, lockfile linter). Add to deployment plan (Step 2).
|