Yuzviak a11ed15187 docs: add Phase 1 ADRs and update PROJECT.md with completed decisions
ADR 0002: hexagonal/ports-and-adapters architecture — components/ layout,
  protocol.py per component, composition root, core/ for concentrated math.
ADR 0003: @dataclass(slots=True, frozen=True) on hot path; Pydantic retained
  only at REST/config/DB boundaries. Pose/GPSPoint migration deferred to Phase 2.
ADR 0004: Stage 2 as independent iteration — own phases 1-6, own requirements,
  stage1 code treated as MVP starting capital.

PROJECT.md: Stage 2 Key Decisions updated from Pending → Accepted with Phase 1
  implementation notes, deferred work list, and final architecture summary.

Co-Authored-By: Claude Sonnet 4.6 <noreply@anthropic.com>
2026-05-11 09:23:09 +03:00

153 lines
13 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# Roadmap: GPS-Denied Onboard Navigation System — Stage 2
**Stage:** 2 (independent iteration)
**Created:** 2026-05-10
**Branch:** `stage2` (HEAD = stage1; v1.0 archived under `.planning/archive/v1.0/`)
**Granularity:** standard
**Total phases:** 6
**Total requirements mapped:** 52 / 52 (100% coverage)
---
## Overview
Stage 2 is a **self-contained iteration** with its own phase numbering (16). It is NOT a continuation of Stage 1's seven phases — those are archived under `.planning/archive/v1.0/` and treated as MVP starting capital (the working ESKF + cuVSLAM/ORB VO + GPR + MAVLink + 195 passing tests).
The Stage 2 mission: refactor the inherited MVP into a hexagonal/ports-and-adapters architecture, re-implement (not merge) selected concept-level ideas from the parallel `try02` branch, formalize acceptance criteria with testable numerics, and add the Azaion 10.05.2026 real-flight integration fixture — all without regressing any of the 195 stage1 tests.
Phases are derived from the ten Stage 2 requirement categories (ARCH, AC, SAFE, VERIFY, FDR, VPR, MAVOUT, FIXTURE, TEST, OBS) and ordered so each phase stabilizes the Protocol surfaces and test infrastructure that the next phase depends on.
## Phase Dependency Order
```
Phase 1 (ARCH — hexagonal refactor + composition root; Protocols stabilized)
Phase 2 (AC + TEST taxonomy + structlog spine — measurement scaffolding)
Phase 3 (SAFE state machine + VERIFY anchor gates — authoritative source labels)
Phase 4 (Conditional Multi-Scale VPR + FDR — uses SAFE triggers, FDR for audit)
Phase 5 (MAVOUT — source-aware GPS_INPUT + spoofing + blackout — needs SAFE labels)
Phase 6 (FIXTURE — Azaion replay + CLI + per-env Docker — exercises everything e2e)
```
## Phases
- [ ] **Phase 1: Hexagonal Refactor & Composition Root** — Reorganize stage1 MVP into `components/` hexagonal layout with Protocol-typed DI composition root; no regressions.
- [ ] **Phase 2: Acceptance Criteria + Test Taxonomy + Observability Spine** — Formal AC document with numeric thresholds, `tests/{unit,integration,blackbox,sitl,e2e}/` taxonomy, structlog correlation_id spine.
- [ ] **Phase 3: Safety Anchor State Machine & Geometry-Gated Verifier** — Authoritative `source_label` ownership + accept/reject gates for satellite anchors before they reach ESKF.
- [ ] **Phase 4: Conditional Multi-Scale VPR + Flight Data Recorder** — Trigger-driven DINOv2 forward, multi-scale FAISS chunks, append-only event log with bounded storage.
- [ ] **Phase 5: MAVLink Source-Aware Output & Spoofing/Blackout Handling** — Source labels + anchor age in GPS_INPUT, spoofing-promotion <3s, visual-blackout dead-reckoning ≤400ms, ODOMETRY scaffold behind feature flag.
- [ ] **Phase 6: Real-Flight Fixture (Azaion 10.05.2026) + CLI + Per-Env Docker** — End-to-end integration test on real flight data, `gps_denied` typer CLI, split Jetson/x86 Dockerfiles.
## Phase Details
### Phase 1: Hexagonal Refactor & Composition Root
**Goal**: Stage1 MVP reorganized into hexagonal/ports-and-adapters layout with explicit DI composition root; all 195 stage1 tests still pass.
**Depends on**: Nothing (first phase; consumes stage1 archived code as input).
**Requirements**: ARCH-01, ARCH-02, ARCH-03, ARCH-04, ARCH-05, ARCH-06, ARCH-07
**Success Criteria** (what must be TRUE):
1. Every swappable component (vio, satellite_matcher, gpr, anchor_verifier, safety_state, flight_recorder, mavlink_io, coordinate_transforms) lives under `src/gps_denied/components/<name>/` with its own `protocol.py` + concrete impls + (where needed) `native/` bridge.
2. Hot-path types (`FrameState`, `IMUSample`, `PositionEstimate`, `VOEstimate`, `SatelliteAnchor`) are `@dataclass(slots=True, frozen=True)` and Pydantic no longer touches the per-frame path.
3. Calling `build_pipeline(env="x86_dev")` / `"jetson"` / `"ci"` / `"sitl"` from `pipeline/composition.py` returns a fully-wired `Pipeline` with environment-correct adapters and no concrete imports leaking into pipeline orchestration.
4. Per-environment YAML configs (`config/{jetson,x86_dev,ci,sitl}.yaml`) load via `pydantic-settings` into a typed `RuntimeConfig` that drives composition.
5. `pytest` runs all 195 stage1 tests (+ 8 SITL skipped) green and accuracy benchmarks show no regression vs the archived stage1 baseline.
**Plans**: TBD
### Phase 2: Acceptance Criteria + Test Taxonomy + Observability Spine
**Goal**: Project gains a formal, testable acceptance-criteria contract, a structured test taxonomy, and a structured-logging spine — the measurement scaffolding every later phase needs to prove its claims.
**Depends on**: Phase 1 (Protocol surfaces and components/ layout must exist before tests/AC can reference them).
**Requirements**: AC-01, AC-02, AC-03, AC-04, AC-05, AC-06, TEST-01, TEST-02, TEST-03, OBS-01
**Success Criteria** (what must be TRUE):
1. `_docs/00_problem/acceptance_criteria.md` lists every AC-1.x…AC-NEW-x with numeric threshold + validation method + linked test ID(s); no AC entry is unbound.
2. `tests/` is reorganized into `unit/integration/blackbox/sitl/e2e/`, every existing test is reclassified, and `pytest -m unit|integration|blackbox|sitl|e2e` selects the right subset for CI.
3. Running `scripts/gen_ac_traceability.py` produces `.planning/AC-TRACEABILITY.md` linking every AC ID → test ID(s) → component(s); CI fails if any AC is orphaned.
4. Position-accuracy, failure-mode, and real-time-performance ACs are wired to `tests/integration/accuracy/`, `tests/blackbox/failure_modes/`, and a benchmark harness that emits CI-tracked metrics.
5. Pipeline emits structured JSON via `structlog` with `correlation_id` (frame_id) on every per-frame log line, and Pydantic logging schemas guard the boundary records.
**Plans**: TBD
### Phase 3: Safety Anchor State Machine & Geometry-Gated Verifier
**Goal**: A separate safety layer — not the ESKF — owns the authoritative `source_label`, enforces monotonic covariance growth in non-anchored modes, and only accepts satellite anchors that pass formal geometric gates.
**Depends on**: Phase 2 (needs AC document + test taxonomy + structlog so state-machine behavior is testable and observable).
**Requirements**: SAFE-01, SAFE-02, SAFE-03, SAFE-04, SAFE-05, SAFE-06, VERIFY-01, VERIFY-02, VERIFY-03, VERIFY-04, VERIFY-05
**Success Criteria** (what must be TRUE):
1. Every emitted `PositionEstimate` carries one of `satellite_anchored / vo_extrapolated / dead_reckoned` set by `SafetyAnchorStateMachine`, plus an `anchor_age_ms` field that increases until the next accepted anchor.
2. Property-based tests prove covariance never decreases without an accepted anchor, and a unit-test matrix exercises all 9 declared state transitions.
3. `GeometryGatedAnchorVerifier` accepts/rejects each candidate using configurable gates (min inliers, max mean reprojection error, max homography condition number, freshness window) and emits a machine-readable rejection reason on every reject.
4. Tile-write eligibility (`can_persist_tile`) is exposed by the state machine and is `false` whenever the system is in `dead_reckoned`, so the tile cache cannot be poisoned during blind flight.
5. The state machine never sees raw VPR top-K candidates — `AnchorVerifier` is the only path that can hand it an accepted anchor — and benchmark mode lets matcher profiles be compared offline on a fixed frame.
**Plans**: TBD
### Phase 4: Conditional Multi-Scale VPR + Flight Data Recorder
**Goal**: DINOv2 retrieval runs only when re-localization is actually needed; chunks are decoupled from storage tiles with multi-scale coverage; every state transition / anchor decision / MAVLink emission is captured in an append-only flight recorder with bounded storage and explicit health states.
**Depends on**: Phase 3 (VPR triggers and FDR events ride on SAFE state-transitions and VERIFY accept/reject decisions).
**Requirements**: VPR-01, VPR-02, VPR-03, VPR-04, VPR-05, FDR-01, FDR-02, FDR-03, FDR-04, FDR-05, FDR-06
**Success Criteria** (what must be TRUE):
1. In steady state the pipeline ranks chunks by IMU+VO geometric prior and skips the DINOv2 forward; DINOv2 runs only on declared re-loc triggers (cold start, sharp turn, σ_xy > 50m, VO failure ≥2 frames, disconnected segment).
2. VPR chunks cover the operating area with 600800m ground footprint and 4050% overlap so any frame footprint falls fully inside ≥1 chunk; FAISS holds both fine-scale (z=20) and coarse-scale (z=17/18) descriptor sets.
3. Top-K is dynamic — K=5 stable, K=20 active-conflict, K=50 expanding-window — and the integration uses the existing `chunk_manager.py` / `gpr.py` API surface without breaking stage1 GPR contracts.
4. `FlightRecorder` writes append-only JSONL segments to `data/fdr/{flight_id}/segment-NNNN.jsonl`, enforces configurable segment + total storage byte limits, and exposes `health ∈ {ok, degraded, critical}`.
5. State transitions, anchor accept/reject decisions, MAVLink sends, and pipeline errors are all recorded as FDR events; AC-NEW-3 forensic thumbnails fire at ≤0.1Hz on tile-generation failures within the FDR size budget.
**Plans**: TBD
### Phase 5: MAVLink Source-Aware Output & Spoofing/Blackout Handling
**Goal**: The MAVLink output the flight controller actually sees carries source provenance and reacts correctly to GPS spoofing and visual blackout, with the dual-channel ODOMETRY path scaffolded but disabled.
**Depends on**: Phase 4 (needs SAFE source labels, FDR audit channel, and VPR triggers to drive blackout/promotion semantics).
**Requirements**: MAVOUT-01, MAVOUT-02, MAVOUT-03, MAVOUT-04
**Success Criteria** (what must be TRUE):
1. Every `GPS_INPUT` message carries `source_label`, `anchor_age_ms`, and `covariance_semimajor_m` propagated from the corresponding `PositionEstimate` (mapped into `horiz_accuracy` and a custom STATUSTEXT for label/age).
2. When real-GPS health rolling average drops below threshold, the system promotes its own estimate to FC primary within <3s and emits a `STATUSTEXT` on every promotion/demotion.
3. When the camera produces no usable signal, the pipeline switches to `dead_reckoned` within ≤1 processed frame OR ≤400ms and emits `VISUAL_BLACKOUT_IMU_ONLY` STATUSTEXT at 12Hz until imagery returns.
4. The `ODOMETRY` emitter exists in code but is disabled by `config.mavlink.odometry_enabled=false` in stage 2, and an integration test asserts ODOMETRY is intentionally absent on the wire.
**Plans**: TBD
### Phase 6: Real-Flight Fixture (Azaion 10.05.2026) + CLI + Per-Env Docker
**Goal**: The whole stack is exercised end-to-end against real flight data, an operator-facing CLI replays flights and runs AC benchmarks, and per-environment Docker images close the deployment loop.
**Depends on**: Phase 5 (final phase — exercises ARCH + AC + SAFE + VERIFY + VPR + FDR + MAVOUT against the Azaion fixture).
**Requirements**: FIXTURE-01, FIXTURE-02, FIXTURE-03, FIXTURE-04, FIXTURE-05, FIXTURE-06, FIXTURE-07, OBS-02, OBS-03
**Success Criteria** (what must be TRUE):
1. `tests/integration/azaion_flight/` runs against `Data/Azaion/10.05.2026/` (tlog + cropped EO video + MAVLink CSV) and is documented in `_docs/00_problem/fixtures.md` with ground-truth references and known limitations.
2. `scripts/prep_azaion_fixture.py` produces HUD-stripped EO frames at 0.7 fps, an IMU/GPS/ATTITUDE CSV from the tlog, and a timestamp-aligned manifest.
3. MAVLink replay decodes every `GLOBAL_POSITION_INT` / `RAW_IMU` / `ATTITUDE` message without error; ESKF replay on the real IMU samples produces no NaN/Inf and shows bounded covariance growth; ORB-SLAM3 VO smoke test achieves ≥30% frame registration on the cropped EO frames.
4. The GPS-denial simulation masks `GPS_RAW_INT` for t∈[180s, 280s] and the pipeline correctly switches to `vo_extrapolated` and back to `satellite_anchored` when GPS returns.
5. `gps_denied` typer CLI exposes `replay --tlog ... --video ...`, `benchmark --scenario ...`, and `bench-ac AC-1.1`; `Dockerfile.x86_dev` and `Dockerfile.jetson` (multi-stage with TRT engine prebuild step) build green and run the replay end-to-end on their respective platforms.
**Plans**: TBD
## Progress
| Phase | Plans Complete | Status | Completed |
|-------|----------------|--------|-----------|
| 1. Hexagonal Refactor & Composition Root | 0/0 | Not started | - |
| 2. Acceptance Criteria + Test Taxonomy + Observability Spine | 0/0 | Not started | - |
| 3. Safety Anchor State Machine & Geometry-Gated Verifier | 0/0 | Not started | - |
| 4. Conditional Multi-Scale VPR + Flight Data Recorder | 0/0 | Not started | - |
| 5. MAVLink Source-Aware Output & Spoofing/Blackout Handling | 0/0 | Not started | - |
| 6. Real-Flight Fixture (Azaion 10.05.2026) + CLI + Per-Env Docker | 0/0 | Not started | - |
## Coverage Summary
| Category | Count | Phase |
|----------|-------|-------|
| ARCH | 7 | Phase 1 |
| AC | 6 | Phase 2 |
| TEST | 3 | Phase 2 |
| OBS-01 | 1 | Phase 2 |
| SAFE | 6 | Phase 3 |
| VERIFY | 5 | Phase 3 |
| VPR | 5 | Phase 4 |
| FDR | 6 | Phase 4 |
| MAVOUT | 4 | Phase 5 |
| FIXTURE | 7 | Phase 6 |
| OBS-02, OBS-03 | 2 | Phase 6 |
| **Total** | **52** | **6 phases** |
100% of Stage 2 requirements mapped; no orphans; no duplicates.