Steps 16 (Deploy) and 17 (Retrospective) outputs for cycle 3. - 03_implementation/deploy_cycle3_report.md — ui/ dev pushed (15838c5..09449bd, 5 commits); stage/prod cutover deferred per push-scope gate option A. - 06_metrics/retro_2026-05-13_cycle3.md — cycle 3 retro: 6/9 pts shipped (AZ-510, AZ-511); AZ-512 deferred to backlog at cross-workspace prereq gate (AZ-513 filed on admin/). - 06_metrics/structure_2026-05-13.md — structural snapshot referenced by retro. - LESSONS.md — appended 3 cycle-3 lessons (process x2, architecture x1). - _autodev_state.md — cycle 3 closed; cycle 4 Step 9 not started. Co-authored-by: Cursor <cursoragent@cursor.com>
18 KiB
Retrospective — 2026-05-13 (Phase B Cycle 3)
Mode: cycle-end (autodev existing-code Step 17)
Scope: Phase B, cycle 3 (state.cycle = 3)
Epic: AZ-509 (UI workspace cycle 3 — Auth bootstrap fix + classColors carve-out + admin edit)
Cycle duration: 3 batches over 1 working day (2026-05-13)
Previous retro: _docs/06_metrics/retro_2026-05-12_cycle2.md (cycle 2)
Implementation Summary
| Metric | Value | Δ vs cycle 2 |
|---|---|---|
| Tasks attempted | 3 (AZ-510, AZ-511, AZ-512) | +1 |
| Tasks delivered | 2 (AZ-510, AZ-511) | 0 |
| Tasks deferred at spec gate | 1 (AZ-512 — cross-workspace prereq) | +1 (new pattern) |
| Total batches | 3 (batch 13, 14, 15) | +1 |
| Total complexity points planned | 9 (3+3+3) | −2 |
| Total complexity points delivered | 6 (3+3) | −5 (cycle 2 shipped 11) |
| Avg tasks per batch | 1 | −1 |
| Avg complexity per (completed) batch | 3 | −2.5 |
| Source files mutated | ~37 production + test (AZ-510 ~25, AZ-511 ~12, AZ-512 0) + 9 docs | n/a (different shape) |
Sources: batch_13_cycle3_report.md, batch_14_cycle3_report.md, batch_15_cycle3_report.md, implementation_report_auth_classcolors_cycle3.md, implementation_completeness_cycle3_report.md, deploy_cycle3_report.md, security_report_cycle3_delta.md.
Quality Metrics
Code Review Results
| Verdict | Count | Percentage | Δ vs cycle 2 |
|---|---|---|---|
| PASS | 2 (batches 13, 14) | 67 % | +2 |
| PASS_WITH_WARNINGS | 0 | 0 % | −1 |
| FAIL | 0 | 0 % | 0 |
| (no formal review — deferred at gate) | 1 (batch 15) | 33 % | n/a |
Note: batch 15 (AZ-512) hit a spec-defined Cross-Workspace Verification BLOCKING gate before implementation began. No source code was written, no review fired. The "no review" row is not a process gap — it is the spec working correctly.
Findings by Severity (code review only)
| Severity | Count | Δ vs cycle 2 |
|---|---|---|
| Critical | 0 | 0 |
| High | 0 | 0 |
| Medium | 0 | 0 |
| Low | 0 | −1 ✓ (cycle 2's pre-existing trim-trailing-slash F1 was not re-flagged because cycle 3 did not touch the affected files) |
Findings by Category (code review)
| Category | Count | Top Files |
|---|---|---|
| Bug | 0 | — |
| Spec-Gap | 0 | — |
| Security | 0 (in code review; security audit fires separately — see below) | — |
| Performance | 0 | — |
| Maintainability | 0 | — |
| Style | 0 | — |
| Scope | 0 | — |
Security-Audit Findings (Step 14 — cycle 3 delta against cycle 2 baseline)
12 carried + 1 new = 13 total. Cycle 3 net delta:
| Status change | Count | Notable IDs |
|---|---|---|
| Closed (HIGH → resolved) | 2 | F-DEP-1 (Vite/PostCSS CVEs — closed by cycle-2-tail bun update), OWASP A07 cold-load gap (closed by AZ-510) |
| Strengthened (defense-in-depth) | 1 | STC-ARCH-01 exemption removed (closed by AZ-511) |
| Newly introduced (LOW) | 1 | F-SAST-CY3-1 — __resetBootstrapInflightForTests exposed via src/auth barrel (AZ-510) |
| Carried forward unchanged (HIGH) | 1 | F-SAST-1 (Google key in mission-planner/ git history; production exposure NONE — see cycle 2 leftover L-AZ-501-GOOGLE-REVOKE) |
| Carried forward unchanged (MEDIUM) | 7 | F-SAST-2/3, F-INF-1..4 (infra hardening backlog) |
Security verdict trajectory: cycle 2 verdict FAIL → cycle 3 verdict PASS_WITH_WARNINGS (driver: all HIGH findings closed; one LOW hygiene item introduced; one HIGH carried at git-history layer with NONE production exposure).
OWASP A06 (Vulnerable & Outdated Components): FAIL → PASS. OWASP A07 (Identification & Authentication Failures): PASS_WITH_KNOWN → PASS.
Structural Metrics
Source: _docs/06_metrics/structure_2026-05-13.md (this cycle), compared against structure_2026-05-12.md (cycle 1 close — cycle 2 introduced no structural changes).
| Metric | Cycle 1 close | Cycle 2 close | Cycle 3 close | Δ vs cycle 2 |
|---|---|---|---|---|
| Component count | 12 | 12 | 12 | 0 |
| Public-API barrels | 11 / 11 (100 %) | 11 / 11 (100 %) | 11 / 11 (100 %) | 0 |
| STC-ARCH-01 carve-out exemptions | 1 (classColors) |
1 | 0 | −1 ✓ |
| Commit-time static gates | 31 / 31 PASS | 33 / 33 PASS | 33 / 33 PASS | 0 (STC-ARCH-01 strengthened, no new gates added) |
| Architecture cycles | 0 | 0 | 0 | 0 |
| Architecture findings open (baseline F1–F9) | 7 of 9 | 7 of 9 | 6 of 9 | −1 ✓ (F3 closed) |
| Newly introduced architecture violations | 0 | 0 | 0 | 0 |
| Net architecture delta this cycle | −2 | 0 | −1 | continued improvement |
Wire-contract assertions (endpoints.test.ts) |
36 | 36 | 37 | +1 (endpoints.admin.usersMe) |
| Fast-profile suite | 209 PASS / 13 SKIP / 0 FAIL | 229 PASS / 13 SKIP / 0 FAIL | 231 PASS / 13 SKIP / 0 FAIL | +2 PASS |
| Bundle (gzipped initial JS) | not measured | 290 465 B | 290 575 B | +110 B (+0.04 %; ~14 % budget) |
Auto-lesson triggers (per skill Step 1)
- Net Architecture delta > 0? No — delta is −1 (improvement). No
architectureregression lesson required. - Structural metric regression > 20 %? No — every structural metric held or improved.
- Contract coverage % decreased? No — wire-contract assertions +1 (37 vs 36).
- New finding category emerged? No — security audit ran in delta mode against the cycle 2 baseline; categories are stable.
Efficiency
| Metric | Value | Δ vs cycle 2 |
|---|---|---|
| Blocked tasks (cycle-internal) | 0 | 0 |
| Tasks deferred to backlog at spec gate | 1 (AZ-512) | +1 (new pattern) |
| Cross-workspace prerequisite tickets filed | 1 (AZ-513 on admin/) |
+1 (new pattern) |
| Pre-existing bugs surfaced as side observations | 1 (AdminPage.tsx add+delete buttons broken end-to-end against live admin/) |
+1 |
| Tasks pending external user action (cycle-3 close) | 7 | +4 vs cycle 2's 3 |
| Tasks requiring fixes after review | 0 | 0 |
| Batch with most findings | none — 0 findings cycle-wide | n/a |
| Auto-fix loops invoked | 0 | 0 |
| Stuck-agent incidents | 0 | 0 |
| Unplanned implementation-time test stabilization loops | 4 in batch 13 (AZ-510 module-scoped state ripple) | +4 (new pattern) |
Blocker Analysis
| Blocker Type | Count | Prevention |
|---|---|---|
| Spec-defined cross-workspace BLOCKING gate (AZ-512) | 1 | Working as intended; the spec design (Cross-Workspace Verification gate) is the prevention. Codify as a reusable task spec template — see Improvement Action #1. |
| Cycle-2 manual third-party action (key revocation) | 2 (carry; not actioned this cycle) | Action #1 from cycle 2 retro still valid; user-action backlog grew rather than drained. See Improvement Action #3. |
| Cycle-2 cross-workspace deploy gate (satellite-provider) | 1 (carry; not actioned this cycle) | Same as above. |
| Cycle-3 deploy push deferred (stage / main / admin/ dev) | 3 (new) | User chose option A (real cutover) but option A in push-scope (ui/ dev only); intentional, but adds to the backlog. |
User-action backlog at cycle close (NEW METRIC — see Improvement Action #3)
| Category | Count | Items |
|---|---|---|
| Manual third-party console action | 2 | L-AZ-499-OWM-REVOKE, L-AZ-501-GOOGLE-REVOKE (carry from cycle 2) |
| Cross-workspace deploy gate | 1 | L-AZ-498-DEPLOY (carry from cycle 2) |
| Cross-workspace prerequisite ticket awaiting sibling-team work | 1 | AZ-513 implementation on admin/ (new this cycle; blocks AZ-512 in _docs/02_tasks/backlog/) |
| Cycle-3 deploy push pending | 3 | D-CY3-STAGE, D-CY3-MAIN, D-CY3-ADMIN-PUSH (new this cycle) |
| Total | 7 | (cycle 1 close: 0 → cycle 2 close: 3 → cycle 3 close: 7) |
This metric is monotonically growing across cycles. The growth is not a process regression — every item is a deliberate conservative-path choice (file prereq ticket vs. invent workaround; defer prod cutover vs. push without satellite-provider gate; etc.) — but the trajectory means the cost of those choices accumulates without an offsetting drain mechanism.
User-decision points (cycle 3 only)
- AZ-512 BLOCKING gate (Cross-Workspace Verification): user skipped the prompt → autodev defaulted to Option A (file prereq ticket on admin/, pause AZ-512). Spec-aligned, conservative, reversible.
- Cycle-3 deploy gate (real cutover vs plan-only): user chose A (real cutover) — first time across cycles 1-3 the user chose anything other than plan-only.
- Cycle-3 push-scope sub-gate: user chose A (ui/ dev only). Stage/main and admin/ dev push deferred.
- Step 14 verdict (PASS_WITH_WARNINGS): no remediation gate fired (only LOW finding); auto-chained.
- Step 15 (Performance Test): no separate report produced; static perf check confirmed green at deploy time (290 575 B / 14 % of budget).
Trend Comparison
| Trend | Cycle 1 | Cycle 2 | Cycle 3 | Direction |
|---|---|---|---|---|
| Code review pass rate (formally-reviewed batches) | 100 % | 50 % (1 PASS_WITH_WARNINGS, 1 no-review sub-step) | 100 % (2/2 reviewed batches PASS) | ⬆ recovered to cycle-1 baseline |
| Test count (cumulative this cycle delta) | +46 | +20 | +2 | declining; cycle 3 was deeper-fix-narrower-surface |
| Static gate count | +2 | +2 | 0 (STC-ARCH-01 strengthened, no new gates) | held |
| Architecture findings open (baseline) | 7 (−2) | 7 (0) | 6 (−1) | ⬆ resumed monotonic decrease |
| STC-ARCH-01 exemptions | 1 | 1 | 0 | first cycle to reach zero |
| Wire-contract assertions | 36 | 36 | 37 (+1) | first growth since cycle 1 |
| Pending USER actions at cycle close | 0 | 3 | 7 | ⬆ ⬆ — accumulating |
| Tasks deferred to backlog at spec gate | 0 | 0 | 1 (AZ-512) | new pattern (working as designed) |
The cycle 3 user-action backlog growth is a structural side-effect of running spec-defined BLOCKING gates correctly, not a process regression. AZ-512's gate caught a cross-workspace dependency that would otherwise have shipped a UI form against a 404 endpoint. The cost is one new entry in the backlog; the alternative was a production-broken affordance.
Top 3 Improvement Actions
-
Codify "Cross-Workspace Verification BLOCKING gate" as a reusable task spec template. AZ-512's spec is the canonical example: pre-implementation gate that requires the implementer to verify a sibling-workspace endpoint exists, with a spec invariant ("Do not invent a workaround that bypasses the missing endpoint") and a fallback-A priority (file prereq ticket on the sibling workspace). Without that gate, batch 15 would have shipped a UI affordance against a 404 endpoint. Future tasks that touch UI ↔ admin / UI ↔ satellite-provider / UI ↔ annotations-service boundaries should always include this gate.
- Impact: high — directly addresses the recurring cross-workspace coordination cost; prevents a class of "ships visibly broken in production" bugs that the AZ-512 /
AdminPage.tsxadd+delete side observation showed already exists in pre-AZ-512 code. - Effort: low — add
_docs/02_tasks/_templates/cross_workspace_dependency.mdwith the gate scaffold (verify-step + spec invariant + 3-option fallback ladder) and reference from.cursor/skills/new-task/SKILL.md"Task Type Detection" section.
- Impact: high — directly addresses the recurring cross-workspace coordination cost; prevents a class of "ships visibly broken in production" bugs that the AZ-512 /
-
Standardize a "module-scoped state introduction" task template / batch checklist. AZ-510's
bootstrapInflightmodule-scoped promise was the right architectural choice for StrictMode-safe bootstrap dedupe but cost ~4 separate fix loops in test setup during implementation: (a)ProtectedRoute.test.tsxhangs from leaked never-resolving promise → fix via test-only reset hook; (b) STC-ARCH-01 violation whentests/setup.tsdeep-imported the helper → fix via barrel re-export; (c) widespread test crashes from default MSW/users/mehandler missingpermissionsfield → fix via defensivehasPermission+ handler seeding; (d) bulk handler swap in 15 test files (http.get('/api/admin/auth/refresh')→http.post) needed because POST production behavior bypassed the existing GET overrides. Each was straightforward in isolation but compounded the batch's wall-clock cost. A pre-implementation checklist would have caught (a)+(b) before code was written.- Impact: medium — directly reduces ripple-cost of architecturally-correct module-scoped state introductions; the pattern recurs anywhere React 18 StrictMode dedupe is needed.
- Effort: low — add
_docs/02_tasks/_templates/module_scoped_state_introduction.md(NEW) with the 4-item checklist (reset-hook plan, afterEach audit, default-fixture invariant check, mock ripple plan); cite AZ-510 as canonical example.
-
Track "user-action backlog at cycle close" as a first-class retrospective metric. Backlog grew 0 → 3 → 7 across cycles 1-3. Each item is a deliberate conservative-path choice (file prereq ticket; defer prod cutover; defer key revocation), but the monotonic accumulation is a process-shape signal. Without a per-cycle measurement and a draining mechanism, the backlog will keep growing and the "cost of conservative defaults" stays invisible. The drain mechanism could be a "Step 0 leftover sweep" in each cycle's first invocation (already partially defined in
tracker.mdcLeftovers Mechanism), but today the autodev does not measure whether the sweep actually moved the backlog count down.- Impact: medium — surfaces accumulating debt that today is only visible by reading the leftovers folder. Makes user-action items first-class deliverables of the process, not silent drag.
- Effort: low — extend
.cursor/skills/retrospective/SKILL.mdStep 1 metric collection with a "user-action backlog" subsection (categories: manual third-party / cross-workspace prereq / cross-workspace deploy / push pending), and add to the retrospective-report template.
Suggested Rule / Skill Updates
| File | Change | Rationale |
|---|---|---|
_docs/02_tasks/_templates/cross_workspace_dependency.md |
NEW file. Pre-implementation BLOCKING gate (verify the prerequisite exists in <sibling/> source); spec invariant ("Do not invent a workaround that bypasses the missing endpoint"); fallback-A priority (file prereq ticket on sibling, pause until lands); options B/C/D for the user; AZ-512 ↔ AZ-513 as canonical example. |
§Top 3 Improvement Action #1. |
.cursor/skills/new-task/SKILL.md (Task Type Detection) |
Add "cross-workspace-dependent" trigger phrase set ("touches admin/", "depends on satellite-provider", "needs new endpoint in <sibling>", "calls /api/admin/<new>") that suggests the new template. |
§Top 3 Improvement Action #1 enablement. |
_docs/02_tasks/_templates/module_scoped_state_introduction.md |
NEW file. 4-item pre-implementation checklist: (a) plan test-only reset hook in same batch; (b) audit afterEach hooks in tests/setup.ts; (c) check default test fixtures still satisfy invariants if helpers consume them; (d) plan ripple swaps in handler mocks (HTTP method / wire shape changes). Cite AZ-510 as canonical example. |
§Top 3 Improvement Action #2. |
.cursor/skills/retrospective/SKILL.md (Step 1 metrics) |
Add "User-action backlog at cycle close" metric: count of unresolved leftover items, broken down by category (manual third-party / cross-workspace prereq / cross-workspace deploy / push pending). Also add cross-workspace prerequisite tickets count and pre-existing bugs surfaced as side observations. | §Top 3 Improvement Action #3. |
.cursor/skills/retrospective/templates/retrospective-report.md |
Add a "User-action backlog at cycle close" subsection under Efficiency with the same category breakdown; include trend across previous cycles. | §Top 3 Improvement Action #3. |
_docs/LESSONS.md (top) |
Append the 3 lessons in §LESSONS Append below; trim to ≤ 15 entries. | Skill Step 4. |
Notes — Step 16 outcome
Step 16 (Deploy) ran in real-cutover mode (option A) for the first time across cycles 1-3. Push scope was ui/ dev only (5 commits, fast-forward 15838c5..09449bd). Stage / main / admin/ dev pushes were deferred at the push-scope sub-gate (user chose option A — ui/ dev only).
- Devices will not auto-pull cycle-3 changes until
dev → stage → maincompletes (D-CY3-STAGE, D-CY3-MAIN). - AZ-513 task spec sits locally on
admin/dev— admin/ team cannot pick it up until D-CY3-ADMIN-PUSH lands. - No Dockerfile /
.woodpecker// nginx / env changes in cycle 3, so no deployment-doc rewrites this cycle (verified viagit diff --stat 70fb452^..HEADon those paths — empty).
These four items add to the user-action backlog; see §Efficiency → User-action backlog table.
LESSONS Append (top 3, single-sentence, tagged)
- [process] When a task spec defines a Cross-Workspace Verification BLOCKING gate and the user skips the choice prompt, the autodev MUST default to the most conservative spec-aligned option (Option A: file prerequisite ticket on the sibling workspace, park the task in
backlog/) — never invent a workaround that bypasses the missing dependency, never silently ship a UI affordance against a non-existent endpoint, and always preserve the user's ability to override at the next invocation, exactly as AZ-512 → AZ-513 demonstrated. - [architecture] Introducing a module-scoped state guard in production source (e.g., a top-level
let bootstrapInflight: Promise | null = nullfor React 18 StrictMode dedupe) requires the same batch to ship 4 coupled changes — (a) a test-only reset hook re-exported via the public barrel (STC-ARCH-01 compliance), (b) anafterEachreset intests/setup.ts, (c) a defensive default-fixture invariant check (e.g., MSW handler must seed required nullable fields the helper consumes), (d) a planned ripple swap in handler mocks for any HTTP method or wire-shape change — skipping any one costs a separate test-stabilization loop, as AZ-510's ~4-attempt arc demonstrated. - [process] Track "user-action backlog at cycle close" as a first-class retrospective metric (count of leftover items broken down by manual-third-party / cross-workspace-prerequisite / cross-workspace-deploy / push-pending categories) — backlog grew monotonically 0 → 3 → 7 across cycles 1-3 and that accumulation is a process-shape signal, not noise; surfacing it makes the cost of conservative-path defaults visible per cycle and creates pressure for an explicit drain mechanism (Step 0 sweep that actually closes items, not just notices them).